Avangrid is developing the Commonwealth Wind project, which will deliver over 1,200 Megawatts of clean, affordable, and renewable electricity to the New England grid.

Commonwealth Wind includes offshore wind turbine generators in Bureau of Ocean Energy Management (BOEM) Lease Area OCS-A 0534 along with associated offshore substation, offshore and onshore cabling, and onshore substation.

Commonwealth Wind is currently engaged in permitting processes at the federal, state, regional, and local level and consulting with tribal groups and federal, state, and local agencies.

Avangrid is committed to responsible development, environmental protection, and minimizing impacts to Barnstable residents, businesses, and visitors during construction of all aspects of the proposed project.

Commonwealth Wind proposes development of utility infrastructure necessary to deliver approximately 1,200 MW of renewable wind power generated in federal waters to the ISO-New England (ISO-NE) regional power grid.

Components of the project located within the Town of Barnstable include:​

  • Installation of three cables through approximately 23 miles of state waters​

  • Approximately 6.7 miles of underground utility infrastructure, running from the landfall site (paved parking lot at Dowses Beach) to the proposed substation ​

  • A proposed substation located on private property north of Route 6, off of Oak Street ​

  • Approximately 0.4 miles of underground utility infrastructure from the proposed substation to the existing West Barnstable Substation, owned by Eversource​

  • New equipment at the existing West Barnstable Substation on Oak Street to facilitate the project’s interconnection into the ISO-NE electrical grid

PROJECT UPDATES

ACTIVE:

COMPLETE:

Frequently Asked Questions:

Sign Up For Email Alerts:

Contact Our Team:

Patrick Johnson
Manager of External Affairs

Rachel Lake
Massachusetts Outreach Coordinator